Scheduled versus tracked time in Jobber: how to find the visits that run long
What I describe here comes from tests I ran in a Jobber test account between Nov 9 and Nov 18, 2026, and from Jobber's help pages as they read that month. Jobber changes its screens from time to time, so yours may look different.
The short answer
Jobber has no report that tells you which visits took longer than planned. But the Visits report carries both numbers for every visit: Schedule duration (what you planned) and Time tracked (what your crew clocked). Export it, put the two side by side and you have the list. Three things trip people up: the two columns use different formats, one counts clock hours while the other counts person-hours, and visits scheduled for "anytime" have no planned duration at all.
An owner asked for exactly this on Jobber's community forum: a monthly check that shows which jobs take longer than expected. Jobber's support team answered that there is no report comparing expected time with actual time, and suggested a custom field for expected hours as a workaround (Jobber Community, Job pricing). You don't need the custom field. The export already has what you need.
What the two columns hold
Schedule duration is the length of the visit as you scheduled it, written as a decimal: a visit from 1:30PM to 4:00PM shows 2.5, irrespective of how big a crew is scheduled for it (Jobber Help, Visits report).
Time tracked is the time your crew recorded on the visit with visit timers, written as hours and minutes: 5:05 means five hours and five minutes. Jobber's help page calls it the cumulative time recorded on the visit.
Conventional wisdom says you subtract one from the other. But the numbers show a different story.
Trap 1: two formats
2.5 and 2:30 are the same length of time. Before you compare anything, turn Time tracked into a decimal (the formula is in the steps below).
Trap 2: clock hours against person-hours
This is the one that matters. Schedule duration is clock time: how long the visit sits on the calendar, whoever is assigned. Time tracked adds up every person's timer.
In my test account, I scheduled a visit from 12:00PM to 4:30PM for a crew of two. The report shows a Schedule duration of 4.5 and 5:05 of Time tracked (3:17 from one person, plus two entries of 0:54 from the other). Side by side that reads as 35 minutes over plan.
It isn't that simple. If both people were meant to work the whole window, the plan was 9 person-hours (two people for 4.5 hours), and the crew used a little over 5. Subtract the columns as they come and every crew of two looks slower than it is. You have to multiply the scheduled hours by the crew size first.
That only works when every person on the crew stays for the whole visit. In this test I had planned for the second person to be there for part of it, and Jobber has no place to say so: the window has one length for the whole crew. For a visit like that, the scheduled hours are not a plan you can check against, with or without the multiplication.
Trap 3: time that isn't there
Three kinds of visits can't be compared this way:
- Anytime visits. A visit scheduled for "anytime" has no start and end, and its Schedule duration is blank.
- Visits without timers. Time tracked only fills when the crew uses the visit timer in the app. If nobody starts it, the column shows 0:00.
- Time entered by hand. In my test, job time added by hand afterwards showed in the Timesheets report but not in the Visits report's Time tracked.
One thing works in your favor. A break stops the visit timer, and Jobber adds the pieces around it: a visit with 0:46 before the break and 1:29 after it counts as one visit of 2:15.
Step by step
- In Jobber, open Insights, then Reports, then Visits (under Work reports).
- Set the date range. Three months is a good start: long enough to see a pattern, short enough to check by hand.
- Click Columns and make sure these are selected: Date, Times, Client name, Assigned to, Visit completed date, Scheduled duration and Time tracked. (On screen the column is called Scheduled duration; in the exported file its header reads Schedule duration, which is the name I use in this article.)
- Click Export to CSV. Jobber emails the file to the address you log in with.
- Open the file in Excel or Google Sheets and remove the rows that can't be compared: no Visit completed date, a blank Schedule duration, or 0:00 in Time tracked.
- Add a column Tracked hours that turns Time tracked into a decimal. If Time tracked is in column F:
=LEFT(F2,FIND(":",F2)-1)+MID(F2,FIND(":",F2)+1,2)/60 - Add a column Crew with the number of people in Assigned to. Jobber writes two people as "A and B" and three as "A, B, and C". Count them by eye, or if Assigned to is in column D:
=IF(D2="",0,IF(ISNUMBER(FIND(",",D2)),LEN(D2)-LEN(SUBSTITUTE(D2,",",""))+1,IF(ISNUMBER(FIND(" and ",D2)),2,1))) - Add a column Planned hours: Schedule duration times Crew. This assumes every person stays on site for the whole visit; where someone joins for part of it, Planned hours comes out too high.
- Add a column Over: Tracked hours minus Planned hours, and next to it the same as a percentage of Planned hours.
- Sort by the percentage, largest first.
A visit from my test account, worked through: one person, scheduled for 1.5 hours, tracked 3:14. That is 3.23 tracked hours against 1.5 planned: 1.73 hours over, more than double.
The two-person visit from above shows the limit. Schedule duration 4.5 and a crew of two give 9.0 planned hours; Time tracked 5:05 is 5.08 hours, which reads as 44% under plan. It wasn't under plan. One of the two was only meant to be there for part of the visit, and the math can't know that.
One visit over plan means little: a locked gate, a new crew member, a customer who wanted to talk. What you are looking for is the customer who shows up near the top of the list again and again. I would look at any customer whose visits run 15% or more over plan most of the time.
When you find one, the plan can be wrong or the job can have grown. If the visit always took this long, fix the schedule. If it used to fit and no longer does, you are looking at scope creep: for a two-person crew, ten extra minutes a visit is $188 a year in wages on one customer.
When there is no scheduled time
Plenty of recurring work is scheduled for "anytime": the crew gets a list for the day, not a slot per customer. Then Schedule duration is blank and there is nothing to compare against. Owners on Jobber's forum describe the same gap from the other side: a service in Jobber carries no expected duration of its own (Jobber Community, Estimated time or duration of jobs).
You can still find the visits that run long. Compare each customer with their own history:
- Keep the Tracked hours column from the steps above.
- Sort by Client name, then by Date.
- For each customer, take the typical tracked time of their first few visits in the file and of their last few. Use the median (the middle value), so one odd visit doesn't decide the result.
- List the customers whose recent visits take clearly longer than their early ones.
This is the better test even when you do have scheduled times. A plan is a guess you made once. A customer's own earlier visits are what the job really took.
What this can't tell you
- Drive time. Time tracked holds time on the visit. The drive to it sits in your timesheets under Driving or General, and belongs to no customer.
- Why a visit ran long. The export shows that it did. Whether the cause was the property, the crew or the customer, you find out by asking.
- Anything for crews that don't use timers. No timer, no tracked time. If only some of your crews track, you can only judge those.
- Visits where part of the crew is on site for part of the time. Jobber schedules one window for the whole crew. If one person is planned for less, the scheduled hours overstate the plan, and the comparison says nothing about that visit.
Next step
A visit that runs long is only half the answer; what it does to your earnings depends on the price. To check one customer, the free bid calculator shows what a visit earns per labor hour with the minutes it takes today.
WellPriced does the history comparison for your whole book from your Jobber exports, drives included, and lists the customers whose revenue per labor hour slipped (how the audit works).
Do you compare planned and tracked time a different way? If so - I'd like to hear how. Tell me about it.
Questions owners ask
Does Jobber have a report for planned versus actual time?
No. Jobber's support team confirmed on the community forum that there is no report comparing expected time with actual time. The Visits report holds both numbers, and you compare them yourself.
Why is Time tracked about double my scheduled time?
Because Time tracked adds up every person's timer, and the scheduled duration is clock time. A crew of two on a 2.5-hour visit tracks about 5 hours.
Why is Schedule duration empty?
The visit was scheduled for "anytime", without a start and end time.
Why does Time tracked show 0:00 on a visit we did?
Nobody ran the visit timer. Time added by hand afterwards shows in the Timesheets report, not here.
How much over plan is a problem?
One visit, not at all. A customer whose visits run 15% or more over plan most of the time is worth a look.
More Jobber how-tos
- How to raise the price of a recurring job in Jobber (without rewriting your history)
- Does Jobber count drive time per client? Where it sits and how to assign it
Sources
- Jobber Help, Visits report (updated Oct 29, 2026)
- Jobber Help, Timesheets (updated Nov 16, 2026)
- Jobber Community, Job pricing
- Jobber Community, Estimated time or duration of jobs
WellPriced isn't affiliated with or endorsed by Jobber. Screens and labels are as I found them in November 2026, and may change.